Construction Management - pdf - both01.pdf
(
54 KB
)
Pobierz
P1: OSO
JWDD004-EP
JWDD004-Halpin-v7
August 24, 2005
18:5
CHAPTER 4
Four Types of Fee Structure
1. Cost
+
Percent of Cost
2. Cost
+
Fixed Fee
+
+
3. Cost
Fixed Fee
Profit Sharing
+
=
−
4. Cost
Sliding fee, Sliding Fee
R
(
2T
A
)
where
T
=
target price,
R
=
base price value,
A
=
actual cost of construction
CHAPTER 7
Forward Pass Equations
EFT(
I
)
=
EST(
I
)
+
DUR(
I
)
all
I
EST(
J
)
=
max [EFT(
I
)]
I
∈
M
where
I
is a member of the set of
M
activities that precede activity
J
.
Backward Pass Equations
LST(
J
)
=
LFT(
J
)
−
DUR(
J
)
all
J
=
LFT(
I
)
min [LST(
J
)]
J
∈
M
where
J
is a member of the set of
M
activities that follow activity
I
.
Four Types of Activity Float
Total Float
TF(I)
=
LFT(I)
−
[EST(I)
+
DUR(I)]
EST(I)
EFT(I)
LFT(I)
EFT(I)
Where I is a member of the set of
preceding activities.
Free Float
all
J
FF(I)
=
min [EST(J)]
−
EFT(I)
J
∈
M
Where J is a member of the set of
follower activities.
Interfering Float
IF(I)
=
TF(I)
−
FF(I)
=
LFT(I)
−
DUR(I)
TF
all J
min[EST(J)]
J M
EST(I)
EFT(I)
FF
DUR(I)
EFT(I)
LFT(I)
DUR(I)
FF
IF
TF
Independent Float
all
J
Ind. F
=
min[EST(J)]
−
LFT(I)
J
∈
M
EST(I)
LST(I)
LFT(I)
min[EST(J)]
DUR(I)
2
P1: OSO
JWDD004-EP
JWDD004-Halpin-v7
August 24, 2005
18:5
CHAPTER 8
PERT Equations
(t
a
+
4t
m
+
t
b
)
Expected duration
t
e
=
6
where
t
a
is the most optimistic duration estimate,
t
m
is the most likely duration estimate,
and
t
b
is the most pessimistic duration estimate.
(t
b
−
2
t
a
)
2
Variance for each PERT activity
σ
=
6
(
X
x
√
Variance
Mean
−
−
x
)
Z
=
or
Z
=
σ
where
σ
is the standard deviation of the cumulative normal distribution.
CHAPTER 9
=
.
+
Pay
1
25(indirect expense
direct expense)
−
.
.
+
0
10[1
25(indirect expense
direct expense)]
Rate of Return
PW
[
REV
(
I
)]
PW
[
EXP
(
I
)]
all
I
all
I
−
=
0
where REV(
I
)
=
revenue for period
I
EXP(
I
)
=
expenditure for period
I
=
PW
present worth of these values
CHAPTER 11
Tire Value
Estimated Service Life in Hours
Purchase Price
−
Depreciation Cost per Hour
=
C
(
n
+
1)
Average Annual Value (AAV)
=
,
2
n
where AAV is the average annual value,
C
is the initial new value of the asset, and
n
is the
number of service life years.
C
(
n
+
1)
+
S
(
n
−
1)
Average Annual Value (AAV), including the salvage value
=
2
n
The hourly charge for IIT is calculated as:
factor
×
delivery price
1000
IIT/hour
=
3
P1: OSO
JWDD004-EP
JWDD004-Halpin-v7
August 24, 2005
18:5
CHAPTER 12
Power Required
=
RR
±
GR
1
1
load factor
Percent swell
=
−
×
100
pounds per cubic yard-loose
pounds per cubic yard-bank
where Load factor
=
Grade Resistance (GR)
=
percent grade
×
20 lb/ton/% grade
×
weight on wheels (tons)
RR
20 lb/ton/% grade
Equivalent percent grade
=
Usable pounds pull
=
(coefficient of traction)
×
(weight on drivers)
CHAPTER 13
Resource-hours per hour
Units per hour
=
RH
/unit, where
RH
=
resource hour
The basic equation for unit pricing:
Resource cost per unit time
Production rate
hr
unit/hr
=
$
/
=
$
/
unit
CHAPTER 15
The five parameters which form the foundation of the “earned” value concept are:
Budgeted Cost of Work Schedule (BCWS)
=
Value of the baseline at a given time
Actual Cost of Worked Performed (ACWP)
−
Measured in the field
Budgeted Cost of Worked Performed (BCWP)
=
[% Complete]
×
BCAC
Budgeted Cost At Completion (BCAC)
=
Estimated Total Cost for the work Package
Actual Quantity of Worked Performed (AQWP)
−
Measured in the field
CV, Cost Variance
=
BCWP
−
ACWP
SV, Schedule Variance
=
BCWP
−
BCWS
CPI, Cost Performance Index
BCWP/ACWP
CPI
<
1.0 indicates cost overrun of budget
CPI
>
1.0 indicates actual cost less than budgeted cost
SPI, Schedule Performance Index
=
=
BCWP/BCWS
P
s
P
c
=
(100
−
P
s
)
where
P
c
=
percentage applied to the project’s total direct cost for the coming year
P
s
=
percentage of total volume in the reference year incurred as fixed or G&A
expense
4
Plik z chomika:
Januszek66
Inne pliki z tego folderu:
Back Seat_ A Mumbai Tale - Aditya Kripalani.mobi
(755 KB)
Brief Wondrous Life of Oscar Wao, The - Junot Diaz.opf
(3 KB)
Don't Make Me Think, Revisited_ - Steve Krug.mobi
(9256 KB)
M. T. Anderson - Norumbegan 03 - The Empire of Gut and Bone # (v5.0).epub
(2209 KB)
M. T. Anderson - Norumbegan 02 - The Suburb Beyond the Stars # (v5.0).epub
(2105 KB)
Inne foldery tego chomika:
Dokumenty
Galeria
LUDLUM ROBERT
Midi - Kar
Mszał Rzymski PL
Zgłoś jeśli
naruszono regulamin