Construction Management - pdf - c18.pdf

(8251 KB) Pobierz
P1: OSO
JWDD004-18
JWDD004-Halpin-v6
August 17, 2005
20:38
Chapter 18
Construction Operations
PROSIDYC: Simulation Program for Construction Operations
The Need
Currently 3D-modelling is the trend in the simulation area. However,
developing 3D models of construction operations is very complex and time
consuming. In general, the study of construction operations requires a tool
that provides solutions without requiring the input of copious amounts of
data. In order for a construction company to use a simulation tool, the
methodology has to be presented in a very simple and graphical context.
Pictorial and schematic tools are easily accepted. In contrast, if the
methodology appears to be too theoretical or analytical it will be avoided
by construction practitioners.
Construction of floating caissons utilized
PROSIDYC as a tool to increase
production.
The Technology
PROSIDYC is a system for simulating construction operations jointly developed by the
Planning and Methods Unit of Dragados y Construcciones, Madrid, Spain and the
Division of Construction Engineering & Management at Purdue University.
PROject SImulation Dragados Y Construcciones (PROSIDYC) is a computer based
system for analyzing construction job site production processes. It is used to improve
productivity in the field by studying resource utilization and cycle times and identifying
opportunities for production improvement. PROSIDYC uses the CYCLic Operations
NEtwork (CYCLONE) modeling format. A set of graphical modeling elements are
utilized to develop a network model of the process of interest. The model identifies
waiting or delay states as well as active productive states. The computer program allows
the modeler to identify resources which are underutilized and bottlenecks in the process.
The use of this approach has achieved 100% success in productivity improvement on
the processes studied. Improvements range from 30% to 200%. Data support the fact that
Harbor site layout.
Caisson Construction Valencia, Spain.
PROSIDYC/CYCLONE
Flow diagram.
18-1
1253325284.025.png 1253325284.026.png 1253325284.027.png 1253325284.028.png 1253325284.001.png 1253325284.002.png 1253325284.003.png
 
P1: OSO
JWDD004-18
JWDD004-Halpin-v6
August 17, 2005
20:38
18-2
Chapter 18
Construction Operations
for every hour of analyst time used, a saving of $2,000 is realized. Therefore, for 100
hours of engineering-time invested, a saving of $200,000 is achieved. PROSIDYC was
used to achieve major cost savings in the massive breakwater in Valencia shown here.
18.1
MODELING CONSTRUCTION OPERATIONS
In Chapter 1, the hierarchy of construction management was described as shown in Figure
18.1. Activities define the structure of projects. The basic building block required to un-
derstand and analyze construction operations is the work task. A meaningful description
of a construction operation requires the definition of the basic work tasks and the manner
in which the available resources (e.g., cranes, crews, materials, etc.) perform or process
through the work tasks. In this sense individual resources can be said to traverse or flow
through work tasks. The sequential and logical relationships between the various work tasks
define the technology being used. The actual working of the operation can then be described
by locating and monitoring, from time to time, the various resource entities as they dynam-
ically traverse the static structure of the operation. A simple graphical modeling system
can be used to analyze the work flow and develop the productivity for a given construction
operation.
18.2
BASIC MODELING ELEMENTS
A modeling format for flow modeling construction operations can be developed using four
graphical symbols:
Figure 18.1 Hierarchical levels in construction management.
1253325284.004.png 1253325284.005.png 1253325284.006.png 1253325284.007.png 1253325284.008.png
 
P1: OSO
JWDD004-18
JWDD004-Halpin-v6
August 17, 2005
20:38
18-3
18.3
Building Process Models
Modeling Element
Name of Element
Description of Modeling Element
The normal work task modeling element can
commence as soon as a unit (e.g. resource)
arrives from a preceding element; it is
unconstrained.
NORMAL
The constrained work task modeling element
requires multiple resources (e.g. cranes,
crews) before it can begin. A combination of
resources is required to start. Otherwise similar
to the normal work task modeling element.
COMBI
The idle state of a resource entity symbolically
represents a waiting location (i.e. a queue)
where resources wait prior to being combined.
QUEUE
The directional flow modeling element shows
the logical flow of resources.
ARROW
Figure 18.2 Basic modeling elements.
1. Active-state square node representing a work task
2. Idle-state circle representing a delay or waiting position for a resource entity
3. Directional flow arrow representing the path of a resource entity as it moves between
idle and active states
The symbols used (see Fig. 18.2) for each modeling element are designed to be simple
and helpful in developing schematic representations of the construction operation being
modeled. Two basic shapes (squares and circles) are used to model active and waiting re-
source states; together with directed arrows (arcs) for resource flow direction, they help to
provide a quick visual grasp of the structure of a construction operation. These symbols
are the basic modeling elements of the CYCLONE (CYCLic Operations Network) mod-
eling system. They are used to build networks of active and idle states to represent cyclic
construction processes.
It is convenient to distinguish between the unconstrained (i.e., normal) work task and
the constrained (i.e., requiring the initial satisfaction of conditions) work task. While all
work tasks are modeled schematically as square nodes, the constrained work task is modeled
as a square node with a corner slash. Thus a total of four symbols is required for the modeling
of the structure and resource entity flow of construction operations (see Fig. 18.2).
The active working-state models are the NORMAL and COMBI modeling elements.
Both have a square-node format and model work tasks. Since the work task is the basic
component of a construction operation, it should be chosen so that its name or description
is sufficient to convey to a crew member or supervisor the nature, technology, work content,
and resources needed to fulfill the work task.
Simple examples of work task activities are breaking open brick pallets, preparing
column formwork, and loading trucks with front-end loaders. The definition of a work task
thus requires a verbal description, an indication of the resource entities involved, and a
definition of the time required (duration) to complete the task.
18.3
BUILDING PROCESS MODELS
The relative sequence and logic of the work tasks and processes that make up a construction
operation constitute the technological structure of the operation. The modeling elements
can be used in a variety of patterns to model construction operations.
1253325284.009.png 1253325284.010.png 1253325284.011.png 1253325284.012.png 1253325284.013.png 1253325284.014.png
 
P1: OSO
JWDD004-18
JWDD004-Halpin-v6
August 17, 2005
20:38
18-4
Chapter 18
Construction Operations
Figure 18.3 Schematic outline of earth-moving operation.
As an example, consider the development of a model for an earth-moving operation
that involves the loading of trucks with earth for transport to a dump area. A pictorial
representation of the operation is shown in Figure 18.3; it uses a front-end loader, some
trucks, and earth.
In order to develop the framework of the earth-moving operation, it is necessary to
identify the major resources involved (i.e., trucks, front-end loader, and soil) and establish
the various states (i.e., both the active working states and the passive waiting states) that
the resources traverse in their work assignment paths and cycles. Finally, the integration of
the resource paths and cycles establishes the basic structure of the operation.
Each truck, for example, is idle while it waits (i.e., queues) for loading; it enters active
working states when it is being loaded, dumping, traveling loaded to the work site, and
returning empty for another load. A simple model of this work cycle is shown in Figure
18.4a using a single COMBI “Load truck” work task that requires earth and a front-end
loader for initiation; three NORMAL work task elements, “Loaded truck travel,” “Truck
dump activity,” and “Empty truck return”; a single QUEUE element, “Join truck queue”;
and five arrows indicating the logical relationships between the various truck states.
18.4
STRUCTURE OF CONSTRUCTION OPERATIONS
The front-end loader can be initially modeled by a unit cycle involving the active-state
COMBI element “FEL (front-end loader) loading,” the idle QUEUE element “FEL idle,”
and two entity flow directional logic arrows (see Fig. 18.4b).
In Figure 18.4c, a soil path model is shown that uses a source QUEUE node “soil
stockpile” and a sink destination soil dump QUEUE node together with a COMBI work
task “Loaded into truck” and NORMAL work tasks “Transport by truck” and “Dumped”
to portray the soil involvement in active work states. Finally, four directional arrows are
required to develop the path structure.
The integrated model incorporating the truck and front-end loader cycles together
with the soil path from stockpile to dump is shown in Figure 18.4d. Model integration is
achieved by combining or “overlaying” active states which are common to two or more
resource cycles. For instance, “load truck” in the truck cycle is the same active state (work
task) as “loaded into truck” in the soil cycle and “FEL Loading” in the loader cycle. These
three states are combined in the integrated model to be one active state “LOAD.”
1253325284.015.png 1253325284.016.png 1253325284.017.png 1253325284.018.png 1253325284.019.png
 
P1: OSO
JWDD004-18
JWDD004-Halpin-v6
August 17, 2005
20:38
18-5
18.5
Modeling Procedure
Figure 18.4 Development of operational structure; (a) truck cycle, (b) loader cycle, and
(c) earth-moving operation.
This model can be used as the basis for further development involving dump area
spotters and queues, dozer stockpiling operations, and truck maintenance, as well as the
basis for further detail such as a more precise description of the front-end loader loading
cycle. An extension of the skeletal structure of the earth-moving operation to include dozer
stockpiling and spreading operations together with a dump spotter foreman is shown in
Figure 18.5. A counter element (represented by a flag) has been added to note the point in
the network at which production will be measured.
The foregoing presentation illustrates that the structure of construction operations can
be developed and illustrated through the proper use and labeling of the basic modeling
elements. The model structure can be used in explaining the construction technology and
construction method of the construction operation to field personnel and managers.
18.5
MODELING PROCEDURE
The procedure for modeling a given construction process involves four basic steps. The
steps, as shown in Figure 18.6, are as follows:
1. Flow Unit Identification .Asafirst step, the modeler must identify the system
resource flow units (e.g., resources such as earth, cranes, crews, etc.) that are
1253325284.020.png 1253325284.021.png 1253325284.022.png 1253325284.023.png 1253325284.024.png
 
Zgłoś jeśli naruszono regulamin